Hello again, I have a task (WorkTimePolicy := whWorkDaysOnly) that starts on October 2, 2025, and is scheduled to last three days. I have also designated October 3 as a holiday. The component is correctly moved in the timeline and the holiday is taken into account. This also works when I insert additional holidays before, but it stops working when I insert additional holidays after that date. Could it be that another bug slipped in with the update?
I have attached a simple sample project so that it can be reproduced.
Thank you in advance for any hints.
GanttHolidayProblem.zip (78.3 KB)